B
BrainBOK
Dashboard
PricingStudy GuideFAQ
Sign InGet Started
DashboardITTO ExplorerQuizFlashcardsExamsStudy Guide
DashboardITTO ExplorerQuizFlashcardsExamsStudy Guide
Study Notes

Crashing vs Fast Tracking — Schedule Compression for PMP

Key differences between crashing and fast tracking schedule compression techniques in project management. Includes when to use each, risks, and PMP exam tips.

You're viewing a free preview of the Study Guide. Upgrade to access all 500+ pages. Upgrade to Plus

Overview

  • Both crashing and fast-tracking are schedule compression techniques.
  • Both techniques aim to compress the project schedule without compromising on the scope.

Crashing

Crashing is a schedule compression technique that involves determining an approach that brings maximum reduction in project duration with least incremental cost and risk, and without changing the scope.

In Crashing, project schedule is compressed by adding more resources to the project, or working overtime to the critical path activities. The key here is "critical path activities". If you apply additional resources to non-critical path activities, it would not result in a compressed schedule.

Drawbacks of Crashing

  • Increased Risks
  • Increased Costs
  • May not always result in a compressed schedule

Fast Tracking

Fast tracking is a schedule compression technique that reduces the project duration by performing critical path activities in parallel that were originally planned to be performed in sequence.

in Fast Tracking, activities which are usually performed in sequence are performed in parallel, to compress the schedule.

As with Crashing, the goal of Fast Tracking is to shorten the duration of the critical path. Therefore, Fast Tracking only works when activities can be overlapped to shorten the critical path duration.

Drawbacks of Fast Tracking

  • Increased Risks (especially quality risks)
  • Rework
  • May also increase project costs

Differences between Crashing and Fast Tracking

In Crashing, schedule is compressed by applying additional resources, working overtime, etc. to critical path activities, whereas in Fast Tracking, activities which are usually performed in sequence are performed in parallel, to compress the schedule.

Crashing vs Fast Tracking Schedule Compression Techniques

In the diagram above, the normal case represents a project with 3 phases, and a duration of 12 weeks with one resource assigned throughout.

With Fast Tracking, some parts of the projects are performed in parallel resulting in a schedule compression by 3 weeks, with one resource assigned throughout. Phase 2 overlaps with phase 1 in weeks 3 and 4, and phase 3 overlaps with phase 2 in week 6.

With Crashing, additional resources are added to the project to compress the schedule by 4 weeks, while performing the phases in sequence. Phase 1 and Phase 2 have two resources assigned, while phase 3 has three resources assigned.

Note that the above example does not imply that Crashing is more effective than Fast Tracking, or the other way around.

Enjoying this article?

BrainBOK members get everything they need to pass the PMP or CAPM — all in one place.

  • 500+ Study Guide pages across all PMP & CAPM domains
  • 2,000+ practice exam questions with full explanations
  • ITTO Explorer — visual maps for all processes & knowledge areas
  • Adaptive flashcards for fast terminology recall
Create Free AccountSee Plans & Pricing
PreviousProject Management Business DocumentsNextCritical Path Method (CPM)

0 / 60 completed

0%

Guide Index
  • Accuracy vs Precision
  • Ambiguity vs Uncertainty
  • Attribute Sampling vs Variable Sampling
  • Common Cause vs Special Cause Variations
  • Communication Channels
  • Complexity Models
  • Configuration Management System
  • Contract Types
  • Control Charts
  • Cost Budget and Reserves
  • Direct Costs vs Indirect Costs
  • Earned Schedule
  • Earned Value Management
  • Estimation in Project Management
  • Expected Monetary Value (EMV)
  • Explicit vs Tacit Knowledge
  • Fist of Five
  • Focus Groups vs Facilitated Workshops
  • Gold Plating
  • Impediments, Obstacles, and Blockers
  • Knowledge vs Information
  • Lean vs Six Sigma
  • MoSCoW Technique
  • Myers-Briggs Type Indicator (MBTI)
  • Non-Functional Requirements in Agile
  • OSCAR Coaching and Mentoring Model
  • Osmotic Communication
  • Personas
  • PMI-isms
  • Product Quality vs Project Quality
  • Product Scope vs Project Scope
  • Progressive Elaboration
  • Project Management Data and Information
  • Project Selection Methods
  • Quality vs Grade
  • Requirement Types
  • Resource Calendar vs Resource Histogram
  • Risk Management Terms
  • Risk Response Strategies
  • Risk vs Issue
  • Roles and Responsibilities
  • Rolling Wave Planning
  • Scope Creep
  • Scope Creep vs Gold Plating
  • Sensitivity Analysis and Tornado Diagram
  • Verification vs Validation
  • Project Management Business Documents
  • Crashing vs Fast Tracking
  • Critical Path Method (CPM)
  • Index
  • Situational Leadership (SLII)
  • Lessons Learned Management Techniques
  • Pondy's Conflict Model
  • Requirements vs Scope - What's the Difference?
  • Resource Leveling vs Resource Smoothing
  • Rule of Seven in Control Charts
  • Situational Questions
  • Stakeholder Classification Models
  • Study Notes Unpublished
  • The Triple Constraints